| Jason Ballard |
5/23/18, 8:00 AM |
7/19/18, 9:30 AM |
7w 2d 1.5h |
38% |
|
| Select a file sharing method. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Select a code repository. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Make a list of candidate programs. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Select a communications tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a task management tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a project we want to tackle. |
5/28/18, 8:00 AM |
5/28/18, 9:00 AM |
1h |
100% |
|
| Select a virtual meeting method. |
5/28/18, 8:40 AM |
5/29/18, 9:00 AM |
> 1d 0.25h |
100% |
|
| Select a management paradigm. |
5/28/18, 9:00 AM |
5/28/18, 10:00 AM |
1h |
100% |
|
| Fill project roles. |
5/28/18, 10:00 AM |
5/28/18, 10:00 AM |
0h |
0% |
|
| Decide whether to schedule physical meetings. |
5/29/18, 9:00 AM |
5/29/18, 9:10 AM |
< 0.25h |
100% |
|
| Edit & receive proposal sign offs from the group. |
5/30/18, 8:00 AM |
5/30/18, 8:30 AM |
0.5h |
100% |
|
| Gather candidate requirement exercises. |
5/30/18, 8:42 AM |
5/31/18, 8:42 AM |
1d |
0% |
|
| Peer assessment for the concept pitch. |
5/30/18, 9:30 AM |
6/1/18, 8:30 AM |
1d 1h |
100% |
|
| Verify and qualify candidate requirements. |
5/31/18, 8:42 AM |
6/1/18, 8:42 AM |
1d |
0% |
|
| Select a language for coding. |
6/1/18, 9:00 AM |
6/1/18, 10:00 AM |
1h |
100% |
|
| Edit & receive SRS sign offs from the group. |
6/4/18, 9:00 AM |
6/4/18, 10:00 AM |
1h |
0% |
|
| Select an architecture |
6/5/18, 8:30 AM |
6/5/18, 9:00 AM |
0.5h |
0% |
|
| Peer assessment for the SRS draft. |
6/5/18, 8:30 AM |
6/5/18, 9:30 AM |
1h |
0% |
|
| Create model and component list. |
6/5/18, 9:00 AM |
6/6/18, 9:00 AM |
1d |
0% |
|
| Verify and qualify the HLD elements. |
6/6/18, 9:00 AM |
6/7/18, 9:00 AM |
1d |
0% |
|
| Edit & receive HLD sign offs from the group. |
6/12/18, 8:12 AM |
6/12/18, 9:12 AM |
1h |
0% |
|
| <GATHER INPUTS>? |
6/12/18, 9:42 AM |
6/22/18, 8:42 AM |
1w 2d 1h |
0% |
|
| Peer assessment for the HLD draft. |
6/12/18, 9:42 AM |
6/13/18, 8:42 AM |
1h |
0% |
|
| Verify and qualify the LLD elements. |
6/22/18, 8:42 AM |
6/29/18, 8:42 AM |
1w |
0% |
|
| Edit & receive LLD sign offs from the group. |
6/29/18, 9:42 AM |
7/2/18, 8:42 AM |
1h |
0% |
|
| Peer assessment for the LLD draft. |
7/2/18, 9:12 AM |
7/3/18, 8:12 AM |
1h |
0% |
|
| Complete our final document review. |
7/16/18, 8:00 AM |
7/16/18, 10:00 AM |
1d |
0% |
|
| Edit & receive final document sign offs from the group. |
7/17/18, 8:00 AM |
7/18/18, 10:00 AM |
2d |
0% |
|
| Peer assessment for the final documents. |
7/19/18, 8:30 AM |
7/19/18, 9:30 AM |
1h |
0% |
|
| Tiffany Harrell |
5/23/18, 8:00 AM |
7/19/18, 9:30 AM |
7w 2d 1.5h |
38% |
|
| Select a file sharing method. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Select a code repository. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Make a list of candidate programs. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Select a communications tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a task management tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a project we want to tackle. |
5/28/18, 8:00 AM |
5/28/18, 9:00 AM |
1h |
100% |
|
| Select a virtual meeting method. |
5/28/18, 8:40 AM |
5/29/18, 9:00 AM |
> 1d 0.25h |
100% |
|
| Select a management paradigm. |
5/28/18, 9:00 AM |
5/28/18, 10:00 AM |
1h |
100% |
|
| Fill project roles. |
5/28/18, 10:00 AM |
5/28/18, 10:00 AM |
0h |
0% |
|
| Decide whether to schedule physical meetings. |
5/29/18, 9:00 AM |
5/29/18, 9:10 AM |
< 0.25h |
100% |
|
| Edit & receive proposal sign offs from the group. |
5/30/18, 8:00 AM |
5/30/18, 8:30 AM |
0.5h |
100% |
|
| Gather candidate requirement exercises. |
5/30/18, 8:42 AM |
5/31/18, 8:42 AM |
1d |
0% |
|
| Peer assessment for the concept pitch. |
5/30/18, 9:30 AM |
6/1/18, 8:30 AM |
1d 1h |
100% |
|
| Verify and qualify candidate requirements. |
5/31/18, 8:42 AM |
6/1/18, 8:42 AM |
1d |
0% |
|
| Select a language for coding. |
6/1/18, 9:00 AM |
6/1/18, 10:00 AM |
1h |
100% |
|
| Edit & receive SRS sign offs from the group. |
6/4/18, 9:00 AM |
6/4/18, 10:00 AM |
1h |
0% |
|
| Select an architecture |
6/5/18, 8:30 AM |
6/5/18, 9:00 AM |
0.5h |
0% |
|
| Peer assessment for the SRS draft. |
6/5/18, 8:30 AM |
6/5/18, 9:30 AM |
1h |
0% |
|
| Create model and component list. |
6/5/18, 9:00 AM |
6/6/18, 9:00 AM |
1d |
0% |
|
| Verify and qualify the HLD elements. |
6/6/18, 9:00 AM |
6/7/18, 9:00 AM |
1d |
0% |
|
| Edit & receive HLD sign offs from the group. |
6/12/18, 8:12 AM |
6/12/18, 9:12 AM |
1h |
0% |
|
| <GATHER INPUTS>? |
6/12/18, 9:42 AM |
6/22/18, 8:42 AM |
1w 2d 1h |
0% |
|
| Peer assessment for the HLD draft. |
6/12/18, 9:42 AM |
6/13/18, 8:42 AM |
1h |
0% |
|
| Verify and qualify the LLD elements. |
6/22/18, 8:42 AM |
6/29/18, 8:42 AM |
1w |
0% |
|
| Edit & receive LLD sign offs from the group. |
6/29/18, 9:42 AM |
7/2/18, 8:42 AM |
1h |
0% |
|
| Peer assessment for the LLD draft. |
7/2/18, 9:12 AM |
7/3/18, 8:12 AM |
1h |
0% |
|
| Complete our final document review. |
7/16/18, 8:00 AM |
7/16/18, 10:00 AM |
1d |
0% |
|
| Edit & receive final document sign offs from the group. |
7/17/18, 8:00 AM |
7/18/18, 10:00 AM |
2d |
0% |
|
| Peer assessment for the final documents. |
7/19/18, 8:30 AM |
7/19/18, 9:30 AM |
1h |
0% |
|
| Jake Hebert |
5/23/18, 8:00 AM |
7/19/18, 9:30 AM |
7w 2d 1.5h |
38% |
|
| Select a file sharing method. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Select a code repository. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Make a list of candidate programs. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Select a communications tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a task management tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a project we want to tackle. |
5/28/18, 8:00 AM |
5/28/18, 9:00 AM |
1h |
100% |
|
| Select a virtual meeting method. |
5/28/18, 8:40 AM |
5/29/18, 9:00 AM |
> 1d 0.25h |
100% |
|
| Select a management paradigm. |
5/28/18, 9:00 AM |
5/28/18, 10:00 AM |
1h |
100% |
|
| Fill project roles. |
5/28/18, 10:00 AM |
5/28/18, 10:00 AM |
0h |
0% |
|
| Decide whether to schedule physical meetings. |
5/29/18, 9:00 AM |
5/29/18, 9:10 AM |
< 0.25h |
100% |
|
| Edit & receive proposal sign offs from the group. |
5/30/18, 8:00 AM |
5/30/18, 8:30 AM |
0.5h |
100% |
|
| Gather candidate requirement exercises. |
5/30/18, 8:42 AM |
5/31/18, 8:42 AM |
1d |
0% |
|
| Peer assessment for the concept pitch. |
5/30/18, 9:30 AM |
6/1/18, 8:30 AM |
1d 1h |
100% |
|
| Verify and qualify candidate requirements. |
5/31/18, 8:42 AM |
6/1/18, 8:42 AM |
1d |
0% |
|
| Select a language for coding. |
6/1/18, 9:00 AM |
6/1/18, 10:00 AM |
1h |
100% |
|
| Edit & receive SRS sign offs from the group. |
6/4/18, 9:00 AM |
6/4/18, 10:00 AM |
1h |
0% |
|
| Select an architecture |
6/5/18, 8:30 AM |
6/5/18, 9:00 AM |
0.5h |
0% |
|
| Peer assessment for the SRS draft. |
6/5/18, 8:30 AM |
6/5/18, 9:30 AM |
1h |
0% |
|
| Create model and component list. |
6/5/18, 9:00 AM |
6/6/18, 9:00 AM |
1d |
0% |
|
| Verify and qualify the HLD elements. |
6/6/18, 9:00 AM |
6/7/18, 9:00 AM |
1d |
0% |
|
| Edit & receive HLD sign offs from the group. |
6/12/18, 8:12 AM |
6/12/18, 9:12 AM |
1h |
0% |
|
| <GATHER INPUTS>? |
6/12/18, 9:42 AM |
6/22/18, 8:42 AM |
1w 2d 1h |
0% |
|
| Peer assessment for the HLD draft. |
6/12/18, 9:42 AM |
6/13/18, 8:42 AM |
1h |
0% |
|
| Verify and qualify the LLD elements. |
6/22/18, 8:42 AM |
6/29/18, 8:42 AM |
1w |
0% |
|
| Edit & receive LLD sign offs from the group. |
6/29/18, 9:42 AM |
7/2/18, 8:42 AM |
1h |
0% |
|
| Peer assessment for the LLD draft. |
7/2/18, 9:12 AM |
7/3/18, 8:12 AM |
1h |
0% |
|
| Complete our final document review. |
7/16/18, 8:00 AM |
7/16/18, 10:00 AM |
1d |
0% |
|
| Edit & receive final document sign offs from the group. |
7/17/18, 8:00 AM |
7/18/18, 10:00 AM |
2d |
0% |
|
| Peer assessment for the final documents. |
7/19/18, 8:30 AM |
7/19/18, 9:30 AM |
1h |
0% |
|
| Abe Hickey |
5/23/18, 8:00 AM |
7/19/18, 9:30 AM |
7w 2d 1.5h |
38% |
|
| Select a file sharing method. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Select a code repository. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Make a list of candidate programs. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Select a communications tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a task management tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a project we want to tackle. |
5/28/18, 8:00 AM |
5/28/18, 9:00 AM |
1h |
100% |
|
| Select a virtual meeting method. |
5/28/18, 8:40 AM |
5/29/18, 9:00 AM |
> 1d 0.25h |
100% |
|
| Select a management paradigm. |
5/28/18, 9:00 AM |
5/28/18, 10:00 AM |
1h |
100% |
|
| Fill project roles. |
5/28/18, 10:00 AM |
5/28/18, 10:00 AM |
0h |
0% |
|
| Decide whether to schedule physical meetings. |
5/29/18, 9:00 AM |
5/29/18, 9:10 AM |
< 0.25h |
100% |
|
| Edit & receive proposal sign offs from the group. |
5/30/18, 8:00 AM |
5/30/18, 8:30 AM |
0.5h |
100% |
|
| Gather candidate requirement exercises. |
5/30/18, 8:42 AM |
5/31/18, 8:42 AM |
1d |
0% |
|
| Peer assessment for the concept pitch. |
5/30/18, 9:30 AM |
6/1/18, 8:30 AM |
1d 1h |
100% |
|
| Verify and qualify candidate requirements. |
5/31/18, 8:42 AM |
6/1/18, 8:42 AM |
1d |
0% |
|
| Select a language for coding. |
6/1/18, 9:00 AM |
6/1/18, 10:00 AM |
1h |
100% |
|
| Edit & receive SRS sign offs from the group. |
6/4/18, 9:00 AM |
6/4/18, 10:00 AM |
1h |
0% |
|
| Select an architecture |
6/5/18, 8:30 AM |
6/5/18, 9:00 AM |
0.5h |
0% |
|
| Peer assessment for the SRS draft. |
6/5/18, 8:30 AM |
6/5/18, 9:30 AM |
1h |
0% |
|
| Create model and component list. |
6/5/18, 9:00 AM |
6/6/18, 9:00 AM |
1d |
0% |
|
| Verify and qualify the HLD elements. |
6/6/18, 9:00 AM |
6/7/18, 9:00 AM |
1d |
0% |
|
| Edit & receive HLD sign offs from the group. |
6/12/18, 8:12 AM |
6/12/18, 9:12 AM |
1h |
0% |
|
| <GATHER INPUTS>? |
6/12/18, 9:42 AM |
6/22/18, 8:42 AM |
1w 2d 1h |
0% |
|
| Peer assessment for the HLD draft. |
6/12/18, 9:42 AM |
6/13/18, 8:42 AM |
1h |
0% |
|
| Verify and qualify the LLD elements. |
6/22/18, 8:42 AM |
6/29/18, 8:42 AM |
1w |
0% |
|
| Edit & receive LLD sign offs from the group. |
6/29/18, 9:42 AM |
7/2/18, 8:42 AM |
1h |
0% |
|
| Peer assessment for the LLD draft. |
7/2/18, 9:12 AM |
7/3/18, 8:12 AM |
1h |
0% |
|
| Complete our final document review. |
7/16/18, 8:00 AM |
7/16/18, 10:00 AM |
1d |
0% |
|
| Edit & receive final document sign offs from the group. |
7/17/18, 8:00 AM |
7/18/18, 10:00 AM |
2d |
0% |
|
| Peer assessment for the final documents. |
7/19/18, 8:30 AM |
7/19/18, 9:30 AM |
1h |
0% |
|
| Andrew Trout |
5/23/18, 8:00 AM |
7/19/18, 9:30 AM |
7w 2d 1.5h |
38% |
|
| Select a file sharing method. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Select a code repository. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Make a list of candidate programs. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Select a communications tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a task management tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a project we want to tackle. |
5/28/18, 8:00 AM |
5/28/18, 9:00 AM |
1h |
100% |
|
| Select a virtual meeting method. |
5/28/18, 8:40 AM |
5/29/18, 9:00 AM |
> 1d 0.25h |
100% |
|
| Select a management paradigm. |
5/28/18, 9:00 AM |
5/28/18, 10:00 AM |
1h |
100% |
|
| Fill project roles. |
5/28/18, 10:00 AM |
5/28/18, 10:00 AM |
0h |
0% |
|
| Decide whether to schedule physical meetings. |
5/29/18, 9:00 AM |
5/29/18, 9:10 AM |
< 0.25h |
100% |
|
| Edit & receive proposal sign offs from the group. |
5/30/18, 8:00 AM |
5/30/18, 8:30 AM |
0.5h |
100% |
|
| Gather candidate requirement exercises. |
5/30/18, 8:42 AM |
5/31/18, 8:42 AM |
1d |
0% |
|
| Peer assessment for the concept pitch. |
5/30/18, 9:30 AM |
6/1/18, 8:30 AM |
1d 1h |
100% |
|
| Verify and qualify candidate requirements. |
5/31/18, 8:42 AM |
6/1/18, 8:42 AM |
1d |
0% |
|
| Select a language for coding. |
6/1/18, 9:00 AM |
6/1/18, 10:00 AM |
1h |
100% |
|
| Edit & receive SRS sign offs from the group. |
6/4/18, 9:00 AM |
6/4/18, 10:00 AM |
1h |
0% |
|
| Select an architecture |
6/5/18, 8:30 AM |
6/5/18, 9:00 AM |
0.5h |
0% |
|
| Peer assessment for the SRS draft. |
6/5/18, 8:30 AM |
6/5/18, 9:30 AM |
1h |
0% |
|
| Create model and component list. |
6/5/18, 9:00 AM |
6/6/18, 9:00 AM |
1d |
0% |
|
| Verify and qualify the HLD elements. |
6/6/18, 9:00 AM |
6/7/18, 9:00 AM |
1d |
0% |
|
| Edit & receive HLD sign offs from the group. |
6/12/18, 8:12 AM |
6/12/18, 9:12 AM |
1h |
0% |
|
| <GATHER INPUTS>? |
6/12/18, 9:42 AM |
6/22/18, 8:42 AM |
1w 2d 1h |
0% |
|
| Peer assessment for the HLD draft. |
6/12/18, 9:42 AM |
6/13/18, 8:42 AM |
1h |
0% |
|
| Verify and qualify the LLD elements. |
6/22/18, 8:42 AM |
6/29/18, 8:42 AM |
1w |
0% |
|
| Edit & receive LLD sign offs from the group. |
6/29/18, 9:42 AM |
7/2/18, 8:42 AM |
1h |
0% |
|
| Peer assessment for the LLD draft. |
7/2/18, 9:12 AM |
7/3/18, 8:12 AM |
1h |
0% |
|
| Complete our final document review. |
7/16/18, 8:00 AM |
7/16/18, 10:00 AM |
1d |
0% |
|
| Edit & receive final document sign offs from the group. |
7/17/18, 8:00 AM |
7/18/18, 10:00 AM |
2d |
0% |
|
| Peer assessment for the final documents. |
7/19/18, 8:30 AM |
7/19/18, 9:30 AM |
1h |
0% |
|
| Tim Woods |
5/23/18, 8:00 AM |
7/19/18, 9:30 AM |
8w 0.5h |
39% |
|
| Select a file sharing method. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Select a code repository. |
5/23/18, 8:00 AM |
5/28/18, 9:00 AM |
3d 1h |
100% |
|
| Make a list of candidate programs. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Group journal entry for the week ending 5/26. |
5/25/18, 8:00 AM |
5/25/18, 10:00 AM |
1d |
100% |
|
| Select a communications tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a task management tool. |
5/25/18, 8:40 AM |
5/28/18, 8:40 AM |
1d |
100% |
|
| Select a project we want to tackle. |
5/28/18, 8:00 AM |
5/28/18, 9:00 AM |
1h |
100% |
|
| Select a virtual meeting method. |
5/28/18, 8:40 AM |
5/29/18, 9:00 AM |
> 1d 0.25h |
100% |
|
| Select a management paradigm. |
5/28/18, 9:00 AM |
5/28/18, 10:00 AM |
1h |
100% |
|
| Fill project roles. |
5/28/18, 10:00 AM |
5/28/18, 10:00 AM |
0h |
0% |
|
| Decide whether to schedule physical meetings. |
5/29/18, 9:00 AM |
5/29/18, 9:10 AM |
< 0.25h |
100% |
|
| Write the project proposal draft. |
5/29/18, 9:00 AM |
5/29/18, 10:00 AM |
1h |
100% |
|
| Edit & receive proposal sign offs from the group. |
5/30/18, 8:00 AM |
5/30/18, 8:30 AM |
0.5h |
100% |
|
| Gather candidate requirement exercises. |
5/30/18, 8:42 AM |
5/31/18, 8:42 AM |
1d |
0% |
|
| Peer assessment for the concept pitch. |
5/30/18, 9:30 AM |
6/1/18, 8:30 AM |
1d 1h |
100% |
|
| Verify and qualify candidate requirements. |
5/31/18, 8:42 AM |
6/1/18, 8:42 AM |
1d |
0% |
|
| Group journal entry for the week ending 6/2. |
6/1/18, 8:00 AM |
6/1/18, 10:00 AM |
1d |
100% |
|
| Select a language for coding. |
6/1/18, 9:00 AM |
6/1/18, 10:00 AM |
1h |
100% |
|
| Edit & receive SRS sign offs from the group. |
6/4/18, 9:00 AM |
6/4/18, 10:00 AM |
1h |
0% |
|
| Select an architecture |
6/5/18, 8:30 AM |
6/5/18, 9:00 AM |
0.5h |
0% |
|
| Peer assessment for the SRS draft. |
6/5/18, 8:30 AM |
6/5/18, 9:30 AM |
1h |
0% |
|
| Create model and component list. |
6/5/18, 9:00 AM |
6/6/18, 9:00 AM |
1d |
0% |
|
| Verify and qualify the HLD elements. |
6/6/18, 9:00 AM |
6/7/18, 9:00 AM |
1d |
0% |
|
| Edit & receive HLD sign offs from the group. |
6/12/18, 8:12 AM |
6/12/18, 9:12 AM |
1h |
0% |
|
| <GATHER INPUTS>? |
6/12/18, 9:42 AM |
6/22/18, 8:42 AM |
1w 2d 1h |
0% |
|
| Peer assessment for the HLD draft. |
6/12/18, 9:42 AM |
6/13/18, 8:42 AM |
1h |
0% |
|
| Verify and qualify the LLD elements. |
6/22/18, 8:42 AM |
6/29/18, 8:42 AM |
1w |
0% |
|
| Edit & receive LLD sign offs from the group. |
6/29/18, 9:42 AM |
7/2/18, 8:42 AM |
1h |
0% |
|
| Peer assessment for the LLD draft. |
7/2/18, 9:12 AM |
7/3/18, 8:12 AM |
1h |
0% |
|
| Complete our final document review. |
7/16/18, 8:00 AM |
7/16/18, 10:00 AM |
1d |
0% |
|
| Edit & receive final document sign offs from the group. |
7/17/18, 8:00 AM |
7/18/18, 10:00 AM |
2d |
0% |
|
| Peer assessment for the final documents. |
7/19/18, 8:30 AM |
7/19/18, 9:30 AM |
1h |
0% |
|
| Cindy Halliday |
6/2/18, 12:00 AM |
7/23/18, 12:00 AM |
< 0.25h |
0% |
|
| Receive project approval. |
6/2/18, 12:00 AM |
6/2/18, 8:42 AM |
0h |
100% |
|
| Receive SRS feedback. |
6/11/18, 9:00 AM |
6/11/18, 9:12 AM |
< 0.25h |
0% |
|
| Receive HLD feedback. |
6/25/18, 9:45 AM |
6/25/18, 9:45 AM |
0h |
0% |
|
| Receive LLD feedback. |
7/16/18, 12:00 AM |
7/16/18, 12:00 AM |
0h |
0% |
|
| Receive final document feedback. |
7/23/18, 12:00 AM |
7/23/18, 12:00 AM |
0h |
0% |
|